Statement of
Principles
PREAMBLE
1. Discussions between the Government of
Newfoundland and Labrador (the "Government") and Inco
Limited and Voisey’s Bay Nickel Company Limited (collectively the
"Proponent" as defined in Schedule A hereto) have resulted
in the following Statement of Principles for the development of the
Voisey's Bay Project as described below (the "Project").
All dollar amounts referred to in the
Statement of Principles are Canadian dollars. All employment levels,
economic and related benefits and costs of facilities referred to in
the Statement of Principles are current estimates.
2. The Statement of Principles is not
intended to and does not create any legally binding rights or
obligations between the parties. The parties will use their best
efforts to finalize mutually acceptable definitive agreements (the
"Binding Agreements") embodying the Statement of
Principles as expeditiously as possible and in any event by
September 30, 2002, subject to paragraph 47.
3. The principal conditions to be met
in order for the Proponent to proceed with the Project are: (a) the
passage into law of any changes to the Mining and Mineral Rights Tax
Act contemplated by the Statement of Principles, (b) the completion
of an Environmental Management Agreement, (c) the completion of
required aboriginal agreements, including Impacts and Benefits
Agreements and the Voisey's Bay chapter in the respective land
claims agreements or other interim arrangements, (d) the issuance of
a mining lease from the Department of Mines and Energy, (e) the
receipt of the Harmful Alteration, Disruption or Destruction of Fish
Habitat authorization from Fisheries and Oceans Canada, and (f) the
arrangement of suitable financing by the Proponent to enable the
Project to be developed on a financially prudent basis.
DESCRIPTION OF THE PROJECT
4. Commencement of the Project will
occur in 2002 with site mobilization work in Voisey's Bay, site
preparation work at Argentia, and commencement of the development of
an Inco Innovation Centre in St. John's.
5. The Proponent intends to construct
an integrated mine and mill/concentrator processing plant at the
Voisey's Bay site in Labrador that will process ore from the
Voisey’s Bay deposits and a hydrometallurgical
nickel/copper/cobalt processing operation at Argentia that will
process the nickel/copper/cobalt concentrate from the
mill/concentrator processing plant at the Voisey's Bay site to a
finished nickel product and be capable of processing concentrate and
intermediate feeds containing nickel from other sources around the
world. This would give the hydrometallurgical processing plant the
capability of operating well beyond the life of the Voisey’s Bay
deposits.
6. An Inco Innovation Centre will be
developed and operated in St. John's in conjunction with Memorial
University of Newfoundland. The Inco Innovation Centre's focus will
be on education and research in mineral exploration, mining and
metallurgical processing.
7. The projected aggregate capital
investment in these and related facilities is estimated to be $2.9
billion over the estimated 30-year life of the Project, including
sustaining capital expenditures. The Proponent will prepare
comprehensive bankable feasibility studies and, based upon those
studies, the Project capital and operating costs and schedule will
be finalized. A phased approach to development will be used that
will include a significant research and development program to
confirm and demonstrate the technological and commercial application
of hydrometallurgical technology to sulphide concentrates and will
include a demonstration plant to be constructed at Argentia.
8. The Project will create
significant employment opportunities in the Province of Newfoundland
and Labrador (the "Province"). The construction phases of
the mine and mill/concentrator processing plant and the
hydrometallurgical processing plant will create 1,700 and 3,000
person-years of employment, respectively.
During the various operating phases, the Project will create the
following estimated employment levels: mine and mill/concentrator
processing plant – 400 people; research and development program
– 200 people; underground exploration – 85 people; underground
mine operations – 800 people; and hydrometallurgical processing
plant – 400 people.
9. The total employment benefits from
the Project are estimated to be 76,000 direct and indirect
person-years over the estimated 30-year life of the Project.
Provincial GDP impact over the same period is estimated to be $11
billion.
UNDERTAKINGS
10. The following undertakings by the
Proponent, together with those of the Government, provide the
framework for the proposed development of the Project.
UNDERTAKINGS BY THE PROPONENT
11. The Proponent is committed to
developing the Project in a manner which provides full and fair
benefits to the people of the Province; has a solid business
footing; provides for a reasonable return to its shareholders;
recognizes metals market conditions; can be reasonably and prudently
financed and can be completed as intended. The Proponent will use
its best efforts to obtain the required financing for the Project in
a timely manner. Comprehensive bankable feasibility studies, as
referred to above in paragraph 7, will be prepared which must
reflect and successfully meet these objectives and the undertakings
by the Proponent and the Government contained in the Statement of
Principles. The Proponent's objective is to have a world-class,
efficient operation which will reflect appropriate employment
levels, productivity requirements and other relevant factors.
Infrastructure and Initial Work Program
12. Commencing in 2002, the Proponent
will undertake site mobilization at Voisey's Bay, including the
establishment of a construction camp, initiation of work on
temporary port facilities, and construction of access roads. At
Argentia, in 2002, the Proponent will complete lease arrangements
for the property and undertake site preparation, including
demolition, fencing, security and signage. The Proponent will also
construct a warehouse building and establish staging areas and lay
down areas in support of Labrador activities and establish a project
office and information centre. Site selection, architectural design
and engineering work for the Inco Innovation Centre in St. John's
will also be undertaken in 2002 with target completion of the Inco
Innovation Centre in 2004. This infrastructure and initial work
program, in aggregate, is expected to employ approximately 250
persons. The Proponent will spend a minimum of $55 million on this
program in the Province by March 31, 2003.
Hydrometallurgical Process Research and
Development
13. Commencing in 2002 with
infrastructure development, the Proponent will initiate a
hydrometallurgical process research and development program which
will include the construction and operation of a demonstration plant
at Argentia, at an estimated cost of $130 million. The research and
development program will include the evaluation of chemical
engineering sub-processes for the hydrometallurgical process as well
as the mechanical equipment design for this demonstration plant. The
demonstration plant, scheduled to be operational in 2006, will be
used to establish the commercial, technical and economic feasibility
of the hydrometallurgical process technology for the Voisey’s Bay
nickel/copper/cobalt concentrate. The Proponent will ship
nickel/copper/cobalt concentrate from the Voisey's Bay mine and
mill/concentrator processing plant to the demonstration plant
following successful start up of the mine and mill/concentrator
processing plant.
14. The Proponent will provide an
annual confidential progress report to the Government on the results
of its research and development efforts on hydrometallurgical
process technology containing sufficient documentation to enable the
Government to evaluate the Proponent’s progress in developing the
hydrometallurgical process technology.
15. Site development for the
demonstration plant at Argentia will begin in 2002. Following the
initial development activities in late 2002 and early 2003, the
Proponent will continue to develop the site in preparation for the
demonstration plant and ultimately the commercial processing plant.
The initiatives in support of this presence will include operation
of an information centre, preparation of environmental baseline
studies and continued upgrading or replacement of utility services
required for the demonstration plant and maintaining staging areas.
Additionally, cleanup and civil works on the larger area of the
Argentia peninsula will be initiated. This will consist of
demolition, grading and earthworks construction.
16. The Proponent will explore
business opportunities for the ongoing utilization of the
demonstration plant facilities for the evaluation of other
concentrates and intermediate feeds upon completion of the Voisey's
Bay hydrometallurgical research and development program referred to
in paragraph 13.
Mine and Mill/Concentrator Processing Plant
17. Construction of an open pit mine and
mill/concentrator processing plant at Voisey's Bay, capable of
processing 6,000 tonnes of ore per day, is scheduled to begin in
2003. These facilities are estimated to require 3 years to construct
at a cost of approximately $710 million. The open pit mine and
mill/concentrator processing plant will generate approximately 1,700
person-years of employment during the construction period and will
employ approximately 400 people in operations. The mill/concentrator
processing plant will produce two separate concentrates: a copper
concentrate that will be sold on the open market and a
nickel/copper/cobalt concentrate that will be processed initially at
the Proponent's operations in Ontario and Manitoba and subsequently
at the commercial hydrometallurgical processing plant at Argentia.
The Proponent will not ship any nickel/copper/cobalt concentrate out
of the Province in accordance with the Exemption Order referred to
in paragraph 37 until the demonstration plant referred to in
paragraph 13 is operational and ready to test nickel/copper/cobalt
concentrate.
Underground Exploration
18. The Proponent will undertake an
underground exploration program at an estimated cost of $95 million,
which will employ approximately 85 people. The objective of this
underground exploration program will be to confirm underground
mineable reserves and develop a mining plan. The initial phase of
this exploration program will be an advanced surface program at an
estimated cost of $20 million that will start in 2002 with target
completion in 2006. Subsequent underground exploration will be
scheduled to ensure that sufficient ore is available to sustain full
operation of the mill/concentrator processing plant during the
transition from the open pit operations to full underground mining
operations.
Underground Mine Development and
Mill/Concentrator Expansion
19. Subject to completion of a
successful underground exploration program, as part of the long-term
plan for the Project, the Proponent will commence underground mine
development, which will include a mill/concentrator processing plant
expansion, to provide sufficient ore to sustain operation of the
mine and mill/concentrator processing plant. This program is
currently estimated to cost approximately $750 million. The
underground mining operation will result in the employment of 800
people.
20. The Proponent will use the most
efficient and cost-effective mining techniques which are intended to
include state-of-the-art, automated mining technologies. These
technologies will be aimed at lowering operating costs and extending
the Project life.
Hydrometallurgical Processing Plant
21. The Proponent is committed to
processing the Voisey's Bay nickel/copper/cobalt concentrate in the
Province and to maximizing long-term benefits for the people of the
Province. Consequently, the Proponent will use its best efforts to
develop a technically and economically viable hydrometallurgical
process technology. Upon successful development of the technology,
the Proponent will construct a commercial hydrometallurgical
processing plant in the Province for the nickel/copper/cobalt
concentrate. This plant will have the annual capacity to produce
approximately 110 million lbs of cathode nickel, 5 million lbs of
cobalt product and 15 million lbs of copper revert. Employment
during the 3-year construction period will be approximately 3,000
person-years with approximately 400 persons being employed during
operations. The capital cost for this plant is expected to be
approximately $800 million.
22. In the unlikely event that
the Proponent's proposed hydrometallurgical process technology for
the Voisey's Bay nickel/copper/cobalt concentrate is not
technologically or economically feasible, the Proponent will
construct a commercial hydrometallurgical nickel matte processing
facility or other facility incorporating a proven, state-of-the-art
technology to produce a finished nickel product. Such a facility
will have the same annual finished nickel capacity as the
hydrometallurgical processing plant as described in paragraph 21.
The capital cost of such a facility is estimated to be $670 million
and will create approximately 2,500 person-years of employment
during construction and will employ approximately 350 people.
23. By no later than December 31,
2008, the Proponent will provide the Government with its decision as
to whether it will proceed with the engineering and construction of
either the hydrometallurgical processing plant contemplated by
paragraph 21 or such other facility referred to in paragraph 22.
This decision will be supported by a feasibility study that will
include the technical and economic evaluations that are the basis
for the Proponent’s decision. The Proponent will keep the
Government informed of its progress in reaching this decision so as
to enable (1) the Government to determine whether the experts
referred to below will be required, and (2) the Proponent to meet
the December 31, 2008 date referred to herein. The Government will
either accept the Proponent’s decision or, prior to December 31,
2008, engage a mutually acceptable, recognized third party
engineering firm and a mutually acceptable, recognized third party
financial expert to review the Proponent’s decision and make a
determination with respect to such decision. The Government and the
Proponent will accept the determination made by such experts with
respect to which facility the Proponent will construct. By no later
than December 31, 2008, the Proponent will also provide the
Government with an implementation plan (reflecting the determination
made by such experts, if applicable) that provides the schedule for
the completion of the engineering work for, and the construction of,
the selected facility. This facility is to be completed no later
than December 31, 2011. The Proponent will proceed diligently to
complete the detailed engineering for, and construction of, the
selected facility.
24. The Proponent's objective is to
operate the hydrometallurgical processing plant for the Voisey's Bay
nickel/copper/cobalt concentrate, the hydrometallurgical nickel
matte processing facility or other facility beyond the life of the
eventual Voisey's Bay mining operations. Accordingly, the Proponent
will explore technically and economically feasible opportunities for
plant expansion and to secure opportunities to supply the plant with
additional feed from around the world to fully utilize the large
capital investment in the processing facilities in the Province.
Guarantee of Concentrate Replacement
25. In consideration of the Government
granting the Exemption Orders referred to in paragraphs 37, 38, 39
and 40, the Proponent guarantees that it will, prior to the
cessation of mining operations for the Project, commence shipping
into the Province nickel and cobalt concentrate or other form (from
one or more sources worldwide, other than the Project) for
processing in the Province. The quantities of such nickel and cobalt
to be shipped into the Province will be at levels sufficient to
enable either the hydrometallurgical processing plant contemplated
by paragraph 21 or such other facility referred to in paragraph 22
to operate at no less than 50 per cent of the design capacity of
such plant or other facility. These shipments will continue at least
until such time as they total the amount of nickel and cobalt in
concentrate or other form that was shipped from the Province under
the terms of the applicable Exemption Order(s).
The Proponent acknowledges that, if it does not meet its contractual
obligations under this paragraph 25 except for one or more events of
Force Majeure (as defined in Schedule A hereto), (1) the Province
and the economy of the Province will suffer substantial loss if such
nickel and cobalt concentrate or other form is not shipped into and
processed in the Province, and (2) damages are not an adequate
remedy for such breach. However, in the event that damages are
awarded, the Government will be entitled to claim damages for breach
of contract to reflect such losses to the Province and the economy
of the Province for the failure to process such concentrate or other
form in the Province and the Proponent expressly waives any right to
claim or argue that the Government cannot pursue any such suit
against the Proponent.
Inco Innovation Centre
26. The Proponent will establish an Inco
Innovation Centre to be developed and operated in conjunction with
Memorial University of Newfoundland. Work on the Inco Innovation
Centre will commence in 2002 with target completion in 2004. The
Proponent will spend $10 million on the Inco Innovation Centre and
provide an annual endowment of $1 million per year over a 10-year
period to cover operational costs. The Inco Innovation Centre's
focus will be on education and research in mineral exploration,
mining and metallurgical processing. It will provide world-class
education, research and training related to the mining industry to
50-60 students per year engaged in Bachelors, Masters and Doctorate
level programs.
Industrial and Employment Benefits
27. The Proponent will conclude an
Industrial and Employment Benefits Agreement with the Government for
the employment of members of the provincial labour force and for
providing manufacturers, consultants, contractors and service
companies in the Province with a full and fair opportunity to
compete for the supply of goods and services for the Project. The
Proponent will detail plans acceptable to the Government for
monitoring and reporting, on a regular basis, on the efforts of both
itself and its contractors in maximizing benefits to the Province.
This Industrial and Employment Benefits Agreement will include the
Proponent's policies which address principles of full and fair
opportunity in procurement from companies in the Province as well as
training and employment of residents of the Province. These
principles and the Industrial and Employment Benefits Agreement will
recognize the Impacts and Benefits Agreements (IBAs) with the
Labrador Inuit Association and Innu Nation and, pursuant to these
IBAs, the Proponent will encourage the formation of joint ventures
or other forms of cooperative business arrangements between
aboriginal people or firms and other businesses in the Province.
These principles and the Industrial and Employment Benefits
Agreement will highlight:
· Full and Fair Opportunity
How manufacturers, consultants, contractors and service companies
in the Province will be given a full and fair opportunity to
participate on a competitive basis in the supply of goods and
services used in any proposed work or activity.
· First Consideration
– Procurement
How the purchasing practices of the Proponent will provide first
consideration for the procurement of services from within the
Province and for goods manufactured within the Province where
these goods and services are competitive in terms of fair market
price, quality and delivery.
· First Consideration –
Training and Employment
How individual residents in the Province will be given first
consideration for training and employment opportunities in the
work program.
· Supplier Participation
That the Proponent will establish as soon as practical,
Project information centres in St. John's and Happy Valley-Goose
Bay to keep the general public informed about the Project. The
centres will also provide information relating to employment and
supplier procurement opportunities for all phases of the Project
and be receiving points for resumes and tendering/bid
documents. The Proponent will also hold information sessions
throughout the Province regarding supplier participation programs.
· Engineering
That the Proponent will ensure that Project management,
engineering, procurement and Project service activities for the
Project will be carried out in the Province to the greatest extent
possible. Such work will be undertaken by, or have the significant
participation of, Newfoundland and Labrador based firms. When not
available in the Province, specialized expertise will be sourced
and carried out wherever available. In these instances, such firms
from outside the Province will be encouraged to involve
Newfoundland and Labrador engineering firms in these specialized
engineering activities. Further, the Proponent will provide a
human resources plan outlining participation by Newfoundland and
Labrador engineers, geoscientists and other technical disciplines,
along with a plan indicating the opportunities for them to develop
and assume increasingly senior positions as the Project proceeds.
·Newfoundland and Labrador
Construction/ Fabrication Facilities
That the Proponent will make full use of construction, fabrication
and assembly capabilities in the Province by requiring potential
bidders to bid the work using a qualified facility in the Province
in their bid where available. The Proponent will make potential
bidders aware of construction and fabrication facilities in the
Province and the Proponent will direct potential bidders to the
appropriate Government department/official for information on
construction facilities and capabilities in the Province.
Where construction, fabrication and assembly services are
performed in the Province, the Proponent will require contractors
and subcontractors carrying out that work to locate Project
management, fabrication engineering and procurement activity
within the Province.
· Adjacency Principle
That the Proponent will apply its adjacency principle policy to
the delivery of employment and business opportunities related to
the Project, in order to fulfil its commitment made during the
environmental assessment of the mine and mill/concentrator
processing plant.
· Air and Marine Operations
That the Proponent will require the air operation company or
companies retained to provide air transportation for the Project
and the shipping company or companies retained to ship
nickel/copper/cobalt concentrates and finished nickel, and cobalt
and copper reverts, to have a base of operations in the Province
and in the case of shipping to destinations in Canada, that the
vessels be Canadian flagged and crewed and additionally that
the nickel/copper/cobalt concentrate ships be crewed from within
the Province.
28. The Proponent will develop and
implement training initiatives for all phases of the Project in
co-operation with governments, aboriginal groups, labour
organizations, suppliers and training institutions in the Province.
These initiatives will include pre-employment and employment
training programs utilizing in-house and external training
organizations throughout the Province. Specific programs will be
established for training at the Voisey's Bay and Argentia sites.
Maximum use will be made of existing provincial education facilities
near the Project sites.
Aboriginal Participation
29. The Proponent acknowledges that the
Labrador Inuit Association and Innu Nation assert aboriginal rights
and title to the Project area containing the nickel, cobalt and
copper deposits. The Proponent has negotiated and will enter into
Impacts and Benefits Agreements with both aboriginal groups. These
Agreements, when executed, will provide specific industrial and
employment opportunities for certain aboriginal groups residing
adjacent to the mine and mill/concentrator processing plant.
Project Employment
30. The Proponent will implement a
Project employment strategy that is consistent with the Canadian
Charter of Rights and Freedoms, ensures that individuals
resident in the Province are given first consideration for training
and employment opportunities associated with the Project, and
recognizes the adjacency principle referred to in paragraph 27.
Environmental Undertaking Order
31. Subject to revisions required to
reflect the current scope of the Project, the Proponent will abide
by and implement the terms and conditions contained in the Voisey's
Bay Nickel Company Limited Mine and Mill Undertaking Order, which
are applicable to the mine and mill/concentrator processing plant.
Corporate Income Tax – Newfoundland And
Labrador
32. The Proponent will reach an
agreement with the Province on arrangements which, to the extent
permitted by law, will result in an allocation, for the purposes of
Part IV of the Federal Income Tax Regulations, of the
Proponent's gross revenues from the sale or disposition of
nickel/copper/cobalt products, whether in intermediate or final
form, from the Project to the Province.
Force Majeure
33. If the Proponent establishes that
it is prevented from performing any of its obligations under the
Statement of Principles by reason of one or more event(s) of Force
Majeure (as defined in Schedule A hereto), such obligations will be
suspended for the period during which the event(s) of Force Majeure
is/are in effect and the Proponent will be entitled to an extension
of any dates referred to in the Statement of Principles for a
reasonable period of time. However, even though the Proponent’s
obligation(s) will be suspended for the period of time during which
the event(s) of Force Majeure remain(s) in effect, when such event(s)
of Force Majeure is/are no longer in effect, the obligation(s) will
become operative until such obligation(s) are fulfilled.
UNDERTAKINGS BY THE GOVERNMENT
Aboriginal Agreements
34. The Government acknowledges that the
Labrador Inuit Association and Innu Nation assert aboriginal rights
and title to the Project area containing the mineral deposits. The
Government will enter into interim measures agreements or other
alternative agreements with both aboriginal groups that will include
the Voisey's Bay chapter of the respective land claims agreements.
The Government will also enter into an Environmental Management
Agreement with the Labrador Inuit Association and the Innu Nation
with respect to the Project. The Government will use its best
efforts to conclude negotiations on these agreements in a timely
manner.
Electrical Rates and Provision Of Power
35. The Government will commit to cause
Newfoundland and Labrador Hydro to charge the island industrial
electrical rate, or such lower electrical power rate that may be
offered from time to time to customers in comparable circumstances,
for the Proponent's processing facilities located on the island
portion of the Province and that a sufficient power supply will be
available when the commercial hydrometallurgical processing plant
provided for in paragraph 21 or other facility provided for in
paragraph 22 commences operation.
Mining Lease
36. The Government will issue a mining
lease pursuant to the Mineral Act which will provide, among
other things, that the annual production of the mine will be no more
than 2.2 million tonnes of ore during the first 10 years of mining
operations and no more than 5.5 million tonnes of ore
thereafter and that primary processing will take place in the
Province.
Exemption Orders
37. The Government will issue an
Exemption Order that will become effective upon the shipment of
first concentrate to the demonstration plant at Argentia. This
Exemption Order will allow the Proponent to ship out of the Province
a fixed volume of nickel/copper/cobalt concentrate containing a
total of up to 355,000 tonnes of nickel from the date that the
demonstration plant is operational and ready to test
nickel/copper/cobalt concentrate to the date of the commencement of
the commissioning and start up of the hydrometallurgical processing
plant at Argentia contemplated by paragraph 21 or other facility
contemplated by paragraph 22. This Exemption Order will expire upon
the Proponent reaching the volume limit as set out in the Exemption
Order.
This Exemption Order will provide that shipping of
nickel/copper/cobalt concentrate out of the Province will be
suspended if (a) the Proponent has not delivered to the Government
the decision referred to in paragraph 23 by December 31, 2008, or
(b) the Proponent is not proceeding diligently with the detailed
engineering work for, and construction of, the hydrometallurgical
processing plant or other facility thereafter for completion no
later than December 31, 2011, unless the Proponent’s failure to
perform is by reason of one or more event(s) of Force Majeure (as
defined in Schedule A hereto). The determination as to whether the
Proponent is proceeding diligently will be made annually on the
anniversary date of the decision referred to in paragraph 23 by a
mutually acceptable independent licensed engineer certifying whether
the actual construction of the selected facility is on schedule with
the accepted implementation plan.
38. The Government will also issue an
Exemption Order allowing the Proponent to ship out of the Province
an additional fixed volume of nickel/copper/cobalt concentrate
containing a total of up to 85,000 tonnes of nickel, during the
commissioning and ramp up of the hydrometallurgical processing plant
contemplated by paragraph 21.
39. In the event that the Proponent
proceeds with the commercial hydrometallurgical nickel matte
processing facility or other facility provided for in paragraph 22,
the Government will issue an Exemption Order, which will become
effective on the date that such processing facility commences
commissioning and ramping up, that will allow the shipment of all
nickel/copper/cobalt concentrate from the Project out of the
Province, subject to the continued operation of the
hydrometallurgical nickel matte processing facility or other
facility at an operating rate capable of processing the amount of
nickel contained in the nickel/copper/cobalt concentrate produced by
the Voisey’s Bay mill/concentrator processing plant.
This Exemption Order will provide
that shipping of nickel/copper/cobalt concentrate out of the
Province will be suspended during such period(s) that such facility
is not operating, unless it is not operating by reason of one or
more event(s) of Force Majeure (as defined in Schedule A hereto) or
it is not operating temporarily due to routine maintenance or
vacation shutdown.
40. The Government, through the
issuance of an Exemption Order, will allow the Proponent to ship out
of the Province all copper concentrate produced from the Project for
the duration of the Project or until sufficient copper reserves are
discovered by the Proponent to permit commercial processing in the
Province. Should commercial processing of copper be established in
the Province by a third party, the Proponent will offer for sale its
available copper concentrate to such third party for its facility on
prevailing commercial terms and conditions subject to availability
and the Proponent’s existing contractual obligations.
Issuance of Approvals
41. Where the Proponent has submitted all information and data in
compliance with applicable legislation, regulatory provisions and
policies required by the Government for it to issue or grant
necessary permits, authorizations, orders and other approvals in
accordance with the Statement of Principles, the Government will
issue or grant such permits, authorizations, orders and other
approvals on a timely basis.
If the Government does not issue or grant such permits,
authorizations, orders and other approvals on a timely basis, the
Proponent will be entitled to (a) an extension of any dates referred
to in the Statement of Principles for a reasonable period of time,
and (b) an amendment to the Exemption Order referred to in paragraph
37 to allow additional amounts of nickel/copper/cobalt concentrate
to be shipped out of the Province, which amount will be calculated
on the basis of the extension referred to in clause (a) and provided
that the Proponent establishes that it will likely ship out of the
Province the fixed volume of nickel in such Exemption Order prior to
the revised completion date of the hydrometallurgical processing
plant or other facility.
Legislative Framework
42. The Government acknowledges that
the Proponent is relying upon the good faith of the Government to
maintain substantially the legislative and regulatory framework
applicable to the Project as at the date of execution of the
Statement of Principles (the "Framework"), subject to
legislative amendments contemplated in the Statement of Principles
and legislation of general application. The Government will maintain
the Framework consistent with the Statement of Principles, subject
to governmental responsibilities, including responsibility for
ensuring proper management of the Province’s resources, the
protection and maintenance of public health and safety and the
protection of the environment. The Government acknowledges that the
Statement of Principles is consistent with current public law and
governmental responsibilities.
The Proponent acknowledges that the Government, in consideration of
agreeing to maintain the Framework, has relied upon the good faith
of the Proponent to carry out its undertakings as enumerated in the
Statement of Principles and its obligations to be contained in the
Binding Agreements.
Special Project Order
43. The Government will issue a Special
Project Order or Orders under the Labour Relations Act to
ensure a stable labour relations environment throughout the
construction phases of the Project. This Order or these Orders will
include, without limitation, such provisions as no strikes and
lock-outs and the ability to designate the union organization and
employer's representative that will be involved in collective
bargaining.
Corporate Income Tax
44. The Government will provide that the
rate of provincial corporate income tax applicable to the Proponent
will be the lower of the "all provinces average" or the
provincial income tax rate.
45. The Government will undertake to
indemnify the Proponent for any double taxation resulting from an
agreement regarding the allocation of gross revenue for purposes of
Part IV of the Federal Income Tax Regulations.
Mining Taxes
46. The Government will introduce and
support legislation to amend the Mining and Mineral Rights Tax
Act (the "Act") and will undertake that the tax rate,
tax base, and tax credit provision in the amended Act will be no
more onerous to the Proponent than the following:
MINING TAX
Tax Rate
· 16% effective rate
» 15% on 80% of net income
» 20% of 20% of net income
less taxable royalties paid for the grant of the right to
engage in mining operations
Tax Base
· Gross revenue (including hedging
gains or losses related to mine output)
· Less:
» Reasonable operating expenses
directly attributable to mining and processing
» Depreciation
» 25% declining balance
» 100% for new mine assets
» Pre-production expenses over
estimated mine life
» Exploration expenses
incurred in Province – carry forward indefinite period
» Processing allowance
» 8% of milling and
concentrating assets in the Province
» 15% of other processing
assets in the Province
» Maximum of 65% of net
income before processing allowance
Tax Credits
· Provincial corporate income tax
paid in respect of mining income may be used to reduce mining
tax payable for the first 10 years of operation. Maximum
annual credit of $2 million.
Non-deductible Expenses
· Income and capital taxes
· Mining tax
· Professional fees related to tax appeals ·
Interest and other costs of financing
· Donations
· Social and recreational costs not incurred at a remote mine
site
· Payments made pursuant to an IBA
· Amounts in excess of the actual cost of non-arm's length
transactions
Approval by the House of Assembly of the
Province
47. The Proponent acknowledges that the
Government intends to submit the Statement of Principles to the
House of Assembly for its consideration and approval. In the event
such approval is not given, the Statement of Principles will be void
ab initio and neither the Proponent nor the Government will
be liable to the other for any loss, damage, cost or claim
whatsoever resulting therefrom. The Government acknowledges that any
delay in such approval could significantly affect the timing and
other aspects of the Proponent’s commitments under the Statement
of Principles, including those set forth in paragraph 12.
Choice of Law and Forum
48. The Government and the Proponent
acknowledge that (1) the Binding Agreements will be governed by, and
construed in accordance with, the laws of the Province and the
applicable laws of Canada, and (2) they will attorn to the courts of
the Province.
Statement of
Principles
Voisey’s Bay Project
Schedule A
1. For the purposes hereof:
"Person" includes any individual, partnership, limited
partnership, firm, trust, body corporate, unincorporated body of
Persons or association.
"Proponent" means collectively, Inco Limited, Voisey’s Bay
Nickel Company Limited, their respective affiliates as such term is
defined in the Corporations Act, and any Person which together
with any of them by way of partnership, joint venture, subcontract or
otherwise is an owner, operator or developer of the Project as defined
in Paragraph 1 of the Statement of Principles.
"Processing Related Reason" means any situation where the
Proponent is unable to meet its obligations under paragraph 25 of the
Statement of Principles as a result of either (i) the unavailability,
for whatever bona fide reason, of concentrate or other form
from any external or other source, or (ii) the unavailability of
concentrate or other form from any external or other source on terms
which are reasonable commercial terms, including, without limitation,
where the terms relating to price or specifications would make it
uneconomic or technically not feasible for processing in order to meet
the requirements of paragraph 25 of the Statement of Principles.
Subject to the exceptions and
qualifications below, "Force Majeure" means one or more of
the following events:
2. Subject to the exceptions and
qualifications below "Force Majeure" means one or more of
the following events:
(a) acts of God or natural disasters,
adverse weather conditions or other similar occurrences;
(b) acts of war (declared or
undeclared) or conditions arising out of or attributable to any such
acts of war, revolutions, insurrections, civil strife, formal or
informal hostilities, mob violence, riots and similar disturbances,
blockades or any other unlawful acts against public order or
authority;
(c) strikes, lockouts, work stoppages
or labour disturbances, unless directly and proximately caused by an
unlawful act or omission of the Proponent;
(d) delay or failure by suppliers
or transporters of materials, parts, supplies, services or equipment;
contractors’ or sub-contractors’ shortage of, or inability to
obtain, labour, transportation, materials, machinery, equipment,
supplies, utilities or services; or breakdown of equipment, machinery
or facilities, unless caused by or resulting from an unlawful act or
omission of the Proponent;
(e) accidents; and
(f) in respect of the Proponent’s
obligation in paragraph 25, a Processing Related Reason, provided
that, a Processing Related Reason will not be an event of Force
Majeure at any time after 3 years following the cessation of mining
operations for the Project.
3. In order to obtain relief for one or more
event(s) of Force Majeure under the Statement of Principles, the
Proponent will (a) use commercially reasonable efforts to (i) prevent
the occurrence of, (ii) perform its obligations in the face of, and
(iii) terminate such event of Force Majeure (other than the events
described in paragraph 2(c) of this Schedule A) relied upon; and (b)
give notice of such event as soon as reasonably practical.
Back
|